1) In a situation where time becomes more important than cost the project manager should first attempt to: a) Remove resources from critical tasks b) Perform smoothing c) Redefine the critical path d) Perform levelling 2) What can be used to help when managing resources? a) Responsibility assignment matrix b) Histogram c) Work breakdown structure d) Risk register 3) Which of the following extends the project end date as it is resource-constrained? a) Smoothing b) Critical path c) Levelling d) Estimating 4) Which of the following preserves the project end date? a) Smoothing b) Levelling c) Critical path d) Estimating 5) Why might smoothing and levelling be performed? a) Too many resources in the same place at the same time b) To identify when resources are needed c) To reduce the cost of resources d) To keep to the schedule